BREAKDOWN OF UNIT PRICE
Item:240103. Earthwork Road Embankmen 2.5-3.5m
Basis:1000cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
10.400
No.
550.00
5720.00
Mason
0.250
No.
700.00
175.00
Sub-Total(L1)
5895.00
208.18
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sundries,Tools-plant etc
0.100
LS
550.00
55.00
Sub-Total(M2)
55.00
1.94
Total(1)
210.12
Add over head on Total(1)
3.5 %
7.35
Add Profit on Total(1)
10.0 %
21.01
Total(2)
238.49
Add VAT on Unit Price
7.5 %
19.34
Unit Price
257.83
Say
258
per cum