BREAKDOWN OF UNIT PRICE
Item:2413. Bituminous Carpeting -25 mm
Basis:100sft
A3.Stone/ Mosaic/ Admix
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Stone chips-12mm crushed
9.970
cft
178.40
1778.65
Bitumen (60/70 grade)
21.769
kg
56.00
1219.06
Stone dust (2.38 mm down)
1.110
cft
55.00
61.05
Sub-Total(A3)
3058.76
329.25
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Vibratory Roller-2 D-3-5T
0.010
day
5500.00
55.00
PneumatTired Roller-8-10T
0.010
day
5000.00
50.00
Sub-Total(E1)
105.00
11.30
E2.Equipment-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Diesel
0.160
litr
68.00
10.88
Lubricants
0.016
litr
220.00
3.52
Sub-Total(E2)
14.40
1.55
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
0.450
No.
550.00
247.50
Mason
0.020
No.
700.00
14.00
Skilled Labour
0.110
No.
600.00
66.00
Sub-Total(L1)
327.50
35.25
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Fire wood
0.600
mnds
220.00
132.00
Sub-Total(M1)
132.00
14.21
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sundries,Tools-plant etc
0.333
LS
550.00
183.15
Sub-Total(M2)
183.15
19.71
Total(1)
411.27
Add over head on Total(1)
3.5 %
14.39
Add Profit on Total(1)
10.0 %
41.13
Total(2)
466.79
Add VAT on Unit Price
7.5 %
37.85
Unit Price
504.64
Say
505
per sqm