BREAKDOWN OF UNIT PRICE
Item:2414. Dense Bituminous Carpeting -38 mm
Basis:100sft
A3.Stone/ Mosaic/ Admix
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Stone chips-19mm crushed
4.600
cft
218.04
1002.98
Stone chips-12mm crushed
9.200
cft
178.40
1641.28
Bitumen (60/70 grade)
42.177
kg
56.00
2361.91
Stone dust (2.38 mm down)
4.600
cft
55.00
253.00
Sub-Total(A3)
5259.18
566.10
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Vibratory Roller-2 D-3-5T
0.015
day
5500.00
82.50
PneumatTired Roller-8-10T
0.015
day
5000.00
75.00
Sub-Total(E1)
157.50
16.95
E2.Equipment-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Diesel
0.265
litr
68.00
18.02
Lubricants
0.026
litr
220.00
5.72
Sub-Total(E2)
23.74
2.56
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
0.750
No.
550.00
412.50
Mason
0.026
No.
700.00
18.20
Skilled Labour
0.158
No.
600.00
94.80
Sub-Total(L1)
525.50
56.56
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Fire wood
1.130
mnds
220.00
248.60
Sub-Total(M1)
248.60
26.76
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sundries,Tools-plant etc
0.333
LS
550.00
183.15
Sub-Total(M2)
183.15
19.71
Total(1)
688.64
Add over head on Total(1)
3.5 %
24.10
Add Profit on Total(1)
10.0 %
68.86
Total(2)
781.61
Add VAT on Unit Price
7.5 %
63.37
Unit Price
844.99
Say
845
per sqm