Return Main Menu
BREAKDOWN OF UNIT PRICE
Item:2902. Anit-Termite Chem-Brickwork Found
Basis:100cft
A3.Stone/ Mosaic/ Admix
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
DURS BAN 20EC Antitermite
5.000
litr
1050.00
5250.00
Sub-Total(A3)
5250.00
1854.04
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Skilled Labour
0.500
No.
600.00
300.00
Skilled Technician
0.125
no
1200.00
150.00
Sub-Total(L1)
450.00
158.92
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.030
LS
550.00
16.50
Sundries,Tools-plant etc
0.054
LS
550.00
29.70
Sub-Total(M2)
46.20
16.32
Total(1)
2029.27
Add over head on Total(1)
3.5 %
71.02
Add Profit on Total(1)
10.0 %
202.93
Total(2)
2303.22
Add VAT on Unit Price
7.5 %
186.75
Unit Price
2489.97
Say
2490
per cum