BREAKDOWN OF UNIT PRICE
Item:2907. Anit-Termite-Wood Door Fram,Panel
Basis:100sft
A3.Stone/ Mosaic/ Admix
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
DURS BAN 20EC Antitermite
0.500
litr
1050.00
525.00
Kerosene
9.500
litr
68.00
646.00
Sub-Total(A3)
1171.00
126.05
C3.Plastic Door/Win/Par
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brush
1.000
no.
10.00
10.00
Sub-Total(C3)
10.00
1.08
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Painter
0.330
No.
700.00
231.00
Sub-Total(L1)
231.00
24.86
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Scaffolding, TnP,Sundries
0.100
LS
550.00
55.00
Sub-Total(M2)
55.00
5.92
Total(1)
157.91
Add over head on Total(1)
3.5 %
5.53
Add Profit on Total(1)
10.0 %
15.79
Total(2)
179.23
Add VAT on Unit Price
7.5 %
14.53
Unit Price
193.76
Say
194
per sqm