BREAKDOWN OF UNIT PRICE
Item:3032. Rec.Paving Blck-Color-200x100-100
Basis:100sft
A1.Brick/ Blocks
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Rec.blck-200x100x100-Colo
464.000
nos.
28.00
12992.00
Sub-Total(A1)
12992.00
1398.46
A4.Earth/ Sand
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand (FM=0.8)
20.000
cft
16.70
334.00
Sub-Total(A4)
334.00
35.95
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
1.500
No.
550.00
825.00
Mason
0.500
No.
700.00
350.00
Head Mason
0.100
No.
800.00
80.00
Sub-Total(L1)
1255.00
135.09
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.500
LS
550.00
275.00
Sub-Total(M2)
275.00
29.60
Total(1)
1599.10
Add over head on Total(1)
3.5 %
55.97
Add Profit on Total(1)
10.0 %
159.91
Total(2)
1814.98
Add VAT on Unit Price
7.5 %
147.16
Unit Price
1962.14
Say
1962
per sqm