BREAKDOWN OF UNIT PRICE
Item:3033. Conc.Kerb Stone-600x300x100/60
Basis:100no.
A1.Brick/ Blocks
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Kerb-stone-600x300x100/60
100.000
nos.
160.00
16000.00
Sub-Total(A1)
16000.00
160.00
A2.Cement
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement: CEM-II/A,52.5-PCC
1.500
bag
405.00
607.50
Sub-Total(A2)
607.50
6.08
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
2.000
No.
550.00
1100.00
Mason
0.750
No.
700.00
525.00
Skilled Labour
1.000
No.
600.00
600.00
Head Mason
0.250
No.
800.00
200.00
Sub-Total(L1)
2425.00
24.25
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.500
LS
550.00
275.00
Sub-Total(M2)
275.00
2.75
Total(1)
193.08
Add over head on Total(1)
3.5 %
6.76
Add Profit on Total(1)
10.0 %
19.31
Total(2)
219.14
Add VAT on Unit Price
7.5 %
17.77
Unit Price
236.91
Say
237
per each