BREAKDOWN OF UNIT PRICE
Item:3036021. Cladiing Work in Facing-Color-38
Basis:100sft
A1.Brick/ Blocks
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Clading Blk-200X90X38-Col
480.000
nos.
16.00
7680.00
Sub-Total(A1)
7680.00
826.68
A2.Cement
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement: CEM-II/A,52.5-PCC
2.600
bag
405.00
1053.00
Sub-Total(A2)
1053.00
113.34
A4.Earth/ Sand
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand (F.M.1.2)
16.250
cft
19.00
308.75
Sub-Total(A4)
308.75
33.23
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Scaffolding
25.000
sft
10.00
250.00
Sub-Total(E1)
250.00
26.91
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Clading Facing Blk-200x90
100.000
sft
33.55
3355.00
Sub-Total(L2)
3355.00
361.13
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.500
LS
550.00
275.00
Sub-Total(M2)
275.00
29.60
Total(1)
1390.90
Add over head on Total(1)
3.5 %
48.68
Add Profit on Total(1)
10.0 %
139.09
Total(2)
1578.67
Add VAT on Unit Price
7.5 %
128.00
Unit Price
1706.67
Say
1707
per sqm