Return Main Menu
BREAKDOWN OF UNIT PRICE
Item:3036051. Cladiing Work in Facing-15 mm
Basis:100sft
A1.Brick/ Blocks
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Clading Block-420X330X15
67.000
nos.
38.00
2546.00
Sub-Total(A1)
2546.00
274.05
A2.Cement
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement: CEM-II/A,52.5-PCC
2.000
bag
405.00
810.00
Sub-Total(A2)
810.00
87.19
A4.Earth/ Sand
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand (F.M.1.2)
12.500
cft
19.00
237.50
Sub-Total(A4)
237.50
25.56
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Scaffolding
25.000
sft
10.00
250.00
Sub-Total(E1)
250.00
26.91
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Clading Facing Blk-200x90
100.000
sft
33.55
3355.00
Sub-Total(L2)
3355.00
361.13
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.500
LS
550.00
275.00
Sub-Total(M2)
275.00
29.60
Total(1)
804.45
Add over head on Total(1)
3.5 %
28.16
Add Profit on Total(1)
10.0 %
80.44
Total(2)
913.05
Add VAT on Unit Price
7.5 %
74.03
Unit Price
987.08
Say
987
per sqm