PWD RATE SCHEDULE-2022 Updating.. | ||||
---|---|---|---|---|
Click on Code to see the analysis or Go Home | Profit=10%, Overhead=3.5%, VAT=7.5% | |||
02 | EXCAVATION, FILLING, SITE DEVELOPMENT AND PALASIDING | |||
Code | Item | Unit | Cost(Tk.) | Unit Rate(Tk.) |
020101 | Earthwork in Excavation-Layout | sqm | 26.00 |
32 |
020102 | Excavate 1.5m depth 10m lead | cum | 157.00 |
193 |
020103 | Excavat addl 0.5m exceed 1.5m dpt | cum | 26.00 |
32 |
020104 | Excavat addl 1m beyond 10 m lead | cum | 4.00 |
5 |
020105 | Excavat upto 2 m depth | cum | 87.00 |
107 |
020106 | Excavate 4.5-6 m depth | cum | 112.00 |
137 |
020107 | Excavate 9-9.3 m depth | cum | 131.00 |
161 |
0202 | Bailing out water during excavatn | hr | 374.00 |
459 |
0203 | Driving bamboo post 75mm dia | metr | 74.00 |
91 |
0204 | Wooden Bollah drive in palasiding | metr | 525.00 |
644 |
0205 | Palasiding drum sheet excl post | sqm | 528.00 |
648 |
0206 | Hor bracing wooden bollah-1/2spl | metr | 195.00 |
239 |
020701 | Shore protection-excavation-1.5m | sqm | 581.00 |
713 |
020702 | Shore protection excv beyond 1.5 | sqm | 858.00 |
1053 |
0208 | Geotextile-filled earth protectn | sqm | 182.00 |
223 |
0209 | Remove Sludge, Sand-FM.8=1:10 | cum | 952.00 |
1168 |
021001 | Sand Filling-F.M.=0.5 | cum | 909.00 |
1115 |
021002 | Sand Filling-F.M.=0.8 | cum | 973.00 |
1194 |
021003 | Sand Filling-F.M.=1.2 | cum | 1354.00 |
1661 |
021004 | Sand Filling-F.M.=2.2 | cum | 3191.00 |
3915 |
021005 | Quarry/ Crusher Dust Filling | cum | 4798.00 |
5887 |
0211 | Khoa Consolidation-Khoa:LSand=2:1 | cum | 4897.00 |
6009 |
0212 | Khoa Cons-Cement:sand:khoa=1:6:12 | cum | 5480.00 |
6724 |
0213 | Earth Filling with earth availabl | cum | 194.00 |
238 |
0214 | Clearing, disposal earth by truc | cum | 705.00 |
865 |
0215 | Earth Filling by carted by truck | cum | 596.00 |
731 |
021601 | Site Develop by carted by truck | cum | 640.00 |
785 |
021602 | Site Develop by dredging | cum | 421.00 |
517 |
0217 | Mechanical Compaction of Earth | cum | 198.00 |
243 |
021801 | ExcavationPond-Lead 30m,lift-1.5m | cum | 229.00 |
281 |
021802 | ExcavatPond-Addl lift 0.3m,1.5-3m | cum | 8.00 |
10 |
021803 | ExcavatPond-Addl lift 0.3m,3-4.5m | cum | 12.00 |
15 |
021804 | ExcavatPond-Addl lift 0.3m,4.5-6m | cum | 17.00 |
21 |
021805 | ExcavatPnd-Addl lead-03m >30m | cum | 31.00 |
38 |
021901 | Bail-out water-1 cusec DieselPump | hour | 586.00 |
719 |
021902 | Bail-out water-1 cusec ElectrPump | hour | 511.00 |
627 |