03 BRICK SOLING, CC, DPC ETC.
Code Item Unit Cost(Tk.) Unit Rate(Tk.)
030101 One Layer Brick Flat Soling sqm
511.00
627
030102 One Layer SCSB Flat Soling sqm
500.00
614
030201 One Layer Herring Bone Bond (HBB) sqm
788.00
967
030202 One Layer HBB SCSB sqm
840.00
1031
030301 Brick on End Edging metr
119.00
146
030302 Brick (m/c made) on End Edging metr
115.00
141
030303 Brick (SCSB) on End Edging metr
128.00
157
030401 CC (1:3:6)-L.Sand,Brickchip-Found cum
7028.00
8624
030402 CC (1:3:6)-L.Sand,Brickchip-Floor cum
6979.00
8563
030501 CC (1:2:4)-L.Sand,Brickchip-Found cum
8268.00
10145
030502 CC (1:2:4)-L.Sand,Brickchip-Floor cum
8266.00
10143
030601 DPC (1:1.5:3)-Sylhet sand,Stone sqm
1286.00
1578
030602 DPC (1:1.5:3)-Syl.sand,Ston,Admix cum
12910.00
15841
0307 Single Layer Polythene Sheet sqm
41.00
50