BREAKDOWN OF UNIT PRICE
Item:020204C. Deduction-Excavation-SubBas-Brick
Basis:35cft
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Deduction-Sand FM>1.0
0.500
cum
548.22
274.11
Deduction-Brick Chip-40mm
0.500
cum
2361.86
1180.93
Sub-Total(C1)
1455.04
1455.04
Total(1)
1455.04
Add over head on Total(1)
3.5 %
50.93
Add Profit on Total(1)
10.0 %
145.50
Total(2)
196.43
Add VAT on Unit Price
5.5 %
11.43
Unit Price
207.86
Say
208
per Cum