BREAKDOWN OF UNIT PRICE
Item:020501. Excavation-Backfilling-Structure
Basis:3532cft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
60.000
day
60.00
3600.00
Plate Compactor
3.000
day
1400.00
4200.00
Water Tanker
0.250
day
8000.00
2000.00
Sub-Total(A1)
9800.00
98.00
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour-Semi-skilled
5.000
pers
560.00
2800.00
Labour-Un-skilled
55.000
pers
540.00
29700.00
Sub-Total(B1)
32500.00
325.00
Total(1)
423.00
Add over head on Total(1)
3.5 %
14.81
Add Profit on Total(1)
10.0 %
42.30
Total(2)
57.11
Add VAT on Unit Price
5.5 %
3.32
Unit Price
60.43
Say
60
per Cum