BREAKDOWN OF UNIT PRICE
Item:030701A. Bituminous Tack Coat-Plant Work
Basis:10764sft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
6.000
day
60.00
360.00
Bitumen Heater
1.000
day
2300.00
2300.00
Bitumen Distrubutor
0.500
day
9200.00
4600.00
Sub-Total(A1)
7260.00
7.26
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Asplat Mistry
0.500
pers
800.00
400.00
Labour-Semi-skilled
0.500
pers
560.00
280.00
Labour-Un-skilled
4.000
pers
540.00
2160.00
Sub-Total(B1)
2840.00
2.84
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bitumen-60/70(Drum)
0.480
Ton
70000.00
33600.00
Sub-Total(C1)
33600.00
33.60
Total(1)
43.70
Add over head on Total(1)
3.5 %
1.53
Add Profit on Total(1)
10.0 %
4.37
Total(2)
5.90
Add VAT on Unit Price
5.5 %
0.34
Unit Price
6.24
Say
6
per Sqm