BREAKDOWN OF UNIT PRICE
Item:050903A. Weep Holes in Abutment, Wing Wall
Basis:6no.
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
1.000
day
60.00
60.00
Sub-Total(A1)
60.00
10.00
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour-Semi-skilled
0.500
pers
560.00
280.00
Labour-Un-skilled
0.500
pers
540.00
270.00
Sub-Total(B1)
550.00
91.67
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
uPVC Pipe 50mm dia
6.000
m
132.00
792.00
Sub-Total(C1)
792.00
132.00
Total(1)
233.67
Add over head on Total(1)
3.5 %
8.18
Add Profit on Total(1)
10.0 %
23.37
Total(2)
31.55
Add VAT on Unit Price
5.5 %
1.84
Unit Price
33.38
Say
33
per Nos.