BREAKDOWN OF UNIT PRICE
Item:051402B. New and extended brickwork
Basis:35cft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
4.000
day
60.00
240.00
Sub-Total(A1)
240.00
240.00
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mason
1.000
pers
700.00
700.00
Labour-Un-skilled
2.000
pers
540.00
1080.00
Sub-Total(B1)
1780.00
1780.00
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand FM > 1.0
0.380
cum
730.00
277.40
Cement - OPC
0.210
Ton
8800.00
1848.00
1st Class Brick
306.800
Nos.
10.00
3068.00
Sub-Total(C1)
5193.40
5193.40
Total(1)
7213.40
Add over head on Total(1)
3.5 %
252.47
Add Profit on Total(1)
10.0 %
721.34
Total(2)
973.81
Add VAT on Unit Price
5.5 %
56.68
Unit Price
1030.49
Say
1030
per Cum