BREAKDOWN OF UNIT PRICE
Item:060305A. Gully Pit with Steel Grating
Basis:1no.
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
4.000
day
60.00
240.00
Concrete Mixer (7/5)
1.000
day
2300.00
2300.00
Sub-Total(A1)
2540.00
2540.00
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mason
1.000
pers
700.00
700.00
Labour-Un-skilled
2.000
pers
540.00
1080.00
Sub-Total(B1)
1780.00
1780.00
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Coarse Sand FM > 2.5
0.270
cum
1836.00
495.72
Cement - OPC
0.210
Ton
8800.00
1848.00
Reinforcing Bar Grade 60
0.030
Ton
72000.00
2160.00
Crushed Boulder/Gravel<25
0.310
cum
7250.00
2247.50
G.I. Wire. nails etc
0.011
kg
120.00
1.32
Wooden Shutter-use 6 time
10.880
sqm
200.00
2176.00
Steel Grating
1.000
no.
320.00
320.00
Sub-Total(C1)
9248.54
9248.54
Total(1)
13568.54
Add over head on Total(1)
3.5 %
474.90
Add Profit on Total(1)
10.0 %
1356.85
Total(2)
1831.75
Add VAT on Unit Price
5.5 %
106.61
Unit Price
1938.36
Say
1938
per Nos.