Return Main Menu
BREAKDOWN OF UNIT PRICE
Item:060401B. Median with Both sidePC Kerb-1.2m
Basis:7rft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
4.000
day
60.00
240.00
Sub-Total(A1)
240.00
120.00
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour-Semi-skilled
1.000
pers
560.00
560.00
Labour-Un-skilled
1.000
pers
540.00
540.00
Sub-Total(B1)
1100.00
550.00
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand FM > 1.0
0.253
cum
730.00
184.69
Cement - OPC
0.154
Ton
8800.00
1355.20
Pre-cast Kerb
10.000
pcs
85.00
850.00
Sub-Total(C1)
2389.89
1194.95
Total(1)
1864.95
Add over head on Total(1)
3.5 %
65.27
Add Profit on Total(1)
10.0 %
186.49
Total(2)
2116.71
Add VAT on Unit Price
5.5 %
123.19
Unit Price
2239.91
Say
2240
per m