BREAKDOWN OF UNIT PRICE
Item:060401D. PC Kerb along Footpath on RCC Dra
Basis:7rft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
2.000
day
60.00
120.00
Sub-Total(A1)
120.00
60.00
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour-Semi-skilled
0.500
pers
560.00
280.00
Labour-Un-skilled
1.000
pers
540.00
540.00
Sub-Total(B1)
820.00
410.00
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand FM > 1.0
0.125
cum
730.00
91.25
Cement - OPC
0.105
Ton
8800.00
924.00
Pre-cast Kerb
5.000
pcs
85.00
425.00
Sub-Total(C1)
1440.25
720.13
Total(1)
1190.13
Add over head on Total(1)
3.5 %
41.65
Add Profit on Total(1)
10.0 %
119.01
Total(2)
160.67
Add VAT on Unit Price
5.5 %
9.35
Unit Price
170.02
Say
170
per m