BREAKDOWN OF UNIT PRICE
Item:0421010. Supply, fix Wood Gauge 150x25mm
Basis:1m
24.Misc-4
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Paint, Ready Mixed
0.027
ltr
270.00
7.29
Sub-Total(24)
7.29
7.29
35.Wood-5
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Wood, Season, Shil Karai
0.004
cum
88200.00
352.80
Sub-Total(35)
352.80
352.80
80.Laboor-0
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Carpnter
0.302
no.
700.00
211.40
Carpenter, Helper
0.052
no.
550.00
28.60
Sub-Total(80)
240.00
240.00
83.Labour-3a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour, Unskill/ Ordinary
0.019
no.
550.00
10.45
Sub-Total(83)
10.45
10.45
85.Labour-5a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Painter/ Varnisher
0.024
no.
700.00
16.80
Sub-Total(85)
16.80
16.80
Total(1)
627.34
Add over head on Total(1)
3.5 %
21.96
Add Profit on Total(1)
10.0 %
62.73
Total(2)
712.03
Add VAT on Unit Price
7.5 %
57.73
Unit Price
769.76
Say
769.47
per m