BREAKDOWN OF UNIT PRICE
Item:0462010. Fill Expn Jnt sand,bitu-40mm-25mm
Basis:1m
13.Material-3
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand, FM>=2.5
0.001
cum
1900.00
1.90
Sub-Total(13)
1.90
1.90
21.Misc-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bitumen: 80/100
0.541
kg
87.00
47.07
Sub-Total(21)
47.07
47.07
34.Wood-4
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Wood, Fire
0.656
kg
5.90
3.87
Sub-Total(34)
3.87
3.87
83.Labour-3a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour, Skilled
0.025
no.
600.00
15.00
Labour, Unskill/ Ordinary
0.050
no.
550.00
27.50
Sub-Total(83)
42.50
42.50
Total(1)
95.34
Add over head on Total(1)
3.5 %
3.34
Add Profit on Total(1)
10.0 %
9.53
Total(2)
108.21
Add VAT on Unit Price
7.5 %
8.77
Unit Price
116.98
Say
116.51
per m