BREAKDOWN OF UNIT PRICE
Item:0480000. 75mm Brick work (1:3), 1st Class
Basis:1sqm
10.Material-Brick1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bricks: 1st Class
31.000
No.
13.00
403.00
Sub-Total(10)
403.00
403.00
11.Material-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Portland Cement
9.500
kg
10.40
98.80
Sub-Total(11)
98.80
98.80
13.Material-3
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand, FM>=1.5
0.019
cum
1100.00
20.90
Sub-Total(13)
20.90
20.90
83.Labour-3a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour, Unskill/ Ordinary
0.228
no.
550.00
125.40
Sub-Total(83)
125.40
125.40
84.Labour-4
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mason
0.065
no.
700.00
45.50
Mason, Head
0.003
no.
800.00
2.40
Mason, Helper
0.032
no.
590.00
18.88
Sub-Total(84)
66.78
66.78
Total(1)
714.88
Add over head on Total(1)
3.5 %
25.02
Add Profit on Total(1)
10.0 %
71.49
Total(2)
811.39
Add VAT on Unit Price
7.5 %
65.79
Unit Price
877.18
Say
876.96
per sqm