BREAKDOWN OF UNIT PRICE
Item:0480500. 125mm Jally Brick work (1:4)
Basis:1sqm
10.Material-Brick1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bricks: 1st Class
35.000
No.
13.00
455.00
Sub-Total(10)
455.00
455.00
11.Material-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Portland Cement
2.500
kg
10.40
26.00
Sub-Total(11)
26.00
26.00
13.Material-3
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand, FM>=1.5
0.007
cum
1100.00
7.70
Sub-Total(13)
7.70
7.70
83.Labour-3a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour, Unskill/ Ordinary
0.280
no.
550.00
154.00
Sub-Total(83)
154.00
154.00
84.Labour-4
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mason
0.071
no.
700.00
49.70
Mason, Head
0.003
no.
800.00
2.40
Mason, Helper
0.036
no.
590.00
21.24
Sub-Total(84)
73.34
73.34
Total(1)
716.04
Add over head on Total(1)
3.5 %
25.06
Add Profit on Total(1)
10.0 %
71.60
Total(2)
812.71
Add VAT on Unit Price
7.5 %
65.90
Unit Price
878.60
Say
878.21
per sqm