BREAKDOWN OF UNIT PRICE
Item:0815030. Carriag Material Boat within 1km
Basis:1cum
22.Misc-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Diesel/ Fuel
0.182
ltr
109.00
19.84
Sub-Total(22)
19.84
19.84
23.Misc-3
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Lubricant (Mobil Oil)
0.009
ltr
500.00
4.50
Sub-Total(23)
4.50
4.50
80.Laboor-0
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Boat, Engine
0.034
no.
1760.00
59.84
Sub-Total(80)
59.84
59.84
83.Labour-3a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour, Unskill/ Ordinary
1.010
no.
550.00
555.50
Sub-Total(83)
555.50
555.50
Total(1)
639.68
Add over head on Total(1)
3.5 %
22.39
Add Profit on Total(1)
10.0 %
63.97
Total(2)
726.03
Add VAT on Unit Price
7.5 %
58.87
Unit Price
784.90
Say
784.88
per m3/k