BREAKDOWN OF UNIT PRICE
Item:0818030. Carriage Brick Manual Lab 0-250 m
Basis:1tho
83.Labour-3a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour, Unskill/ Ordinary
0.007
no.
550.00
3.85
Sub-Total(83)
3.85
3.85
Total(1)
3.85
Add over head on Total(1)
3.5 %
0.13
Add Profit on Total(1)
10.0 %
0.39
Total(2)
4.37
Add VAT on Unit Price
7.5 %
0.35
Unit Price
4.72
Say
4.93
per th/m