BREAKDOWN OF UNIT PRICE
Item:0819040. Carriage Brick by Boat:2nd km abo
Basis:1tho
22.Misc-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Diesel/ Fuel
0.114
ltr
109.00
12.43
Sub-Total(22)
12.43
12.43
23.Misc-3
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Lubricant (Mobil Oil)
0.006
ltr
500.00
3.00
Sub-Total(23)
3.00
3.00
80.Laboor-0
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Boat, Engine
0.013
no.
1760.00
22.88
Sub-Total(80)
22.88
22.88
Total(1)
38.31
Add over head on Total(1)
3.5 %
1.34
Add Profit on Total(1)
10.0 %
3.83
Total(2)
43.48
Add VAT on Unit Price
7.5 %
3.53
Unit Price
47.00
Say
45.70
per th/k