BREAKDOWN OF UNIT PRICE
Item:1218005. Install Dewateri T/wel 12m 75 PVC
Basis:1no.
14.Material-4
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Stone, Pea Gravel: 6mm
0.368
cum
3300.00
1214.40
Sub-Total(14)
1214.40
1214.40
22.Misc-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Diesel/ Fuel
90.000
ltr
109.00
9810.00
Sub-Total(22)
9810.00
9810.00
23.Misc-3
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Lubricant (Mobil Oil)
1.172
ltr
500.00
586.00
Sub-Total(23)
586.00
586.00
30.Wood Work-0
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bamboo,Barak 7.5m,60-80mm
10.000
No.
320.00
3200.00
Sub-Total(30)
3200.00
3200.00
47.Steel-7
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Wire GI 12 BWG
2.000
kg
120.00
240.00
Sub-Total(47)
240.00
240.00
70.Equipment-0
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cargo Truck (Ex Fuel,Lub)
0.300
no.
5800.00
1740.00
Sub-Total(70)
1740.00
1740.00
71.Equipment-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Tripod Drilling Set-Coplt
0.667
no.
5500.00
3668.50
Sub-Total(71)
3668.50
3668.50
75.Equipment-5
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
75mm Clas D PVC Strainer
6.000
m
418.00
2508.00
75mm Clas C PVC Blind Pip
6.000
m
281.00
1686.00
Sub-Total(75)
4194.00
4194.00
76.Equipment-6
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Centrilizer, 13 mm dia
3.000
set
530.00
1590.00
Disel Operat Engin-1 cuse
1.000
No.
32500.00
32500.00
Sub-Total(76)
34090.00
34090.00
77.Equipment-7
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Pipe GI 75 mm dia 5mm Thk
3.000
m
1400.00
4200.00
Sub-Total(77)
4200.00
4200.00
78.Equipment-8
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
75mm dia Clas C PVC Pipe
10.000
m
281.00
2810.00
Bend, GI 75 mm dia
2.000
No.
416.00
832.00
Sub-Total(78)
3642.00
3642.00
79.Equipment-9
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
PVC Pipe Jointing Adhesiv
1.000
kg
280.00
280.00
Sub-Total(79)
280.00
280.00
81.Labour-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Driller
0.667
no.
700.00
466.90
Driller, Helper
1.167
no.
550.00
641.85
Sub-Total(81)
1108.75
1108.75
83.Labour-3a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour, Skilled
3.500
no.
600.00
2100.00
Labour, Unskill/ Ordinary
10.333
no.
550.00
5683.15
Misc. Sundry-Lab Unskill/
2.000
no.
550.00
1100.00
Sub-Total(83)
8883.15
8883.15
84.Labour-4
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mechanic
0.300
no.
700.00
210.00
Mechanic, Helper
0.500
no.
590.00
295.00
Sub-Total(84)
505.00
505.00
85.Labour-5a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Operator, Pump
4.667
no.
750.00
3500.25
Sub-Total(85)
3500.25
3500.25
Total(1)
80862.05
Add over head on Total(1)
3.5 %
2830.17
Add Profit on Total(1)
10.0 %
8086.20
Total(2)
91778.43
Add VAT on Unit Price
7.5 %
7441.49
Unit Price
99219.92
Say
75845.06
per each