Return Main Menu
BREAKDOWN OF UNIT PRICE
Item:1242020. Supply, fix 40mm Strainer PVC
Basis:1no.
54.Plumbing-4
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Socket, GI 38 mm dia
1.000
No.
90.00
90.00
Sub-Total(54)
90.00
90.00
57.Plumbing-7
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
TubeWell,Strainer PVC 38
1.000
No.
400.00
400.00
Sub-Total(57)
400.00
400.00
83.Labour-3a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Misc. Sundry-Lab Unskill/
0.001
no.
550.00
0.55
Sub-Total(83)
0.55
0.55
85.Labour-5a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plumber
0.354
no.
700.00
247.80
Plumber, Helper
0.118
no.
550.00
64.90
Sub-Total(85)
312.70
312.70
Total(1)
803.25
Add over head on Total(1)
3.5 %
28.11
Add Profit on Total(1)
10.0 %
80.33
Total(2)
911.69
Add VAT on Unit Price
7.5 %
73.92
Unit Price
985.61
Say
985.98
per each