Return Main Menu
BREAKDOWN OF UNIT PRICE
Item:1611020. Earthwork Manual emb/bank/road 4m
Basis:1cum
83.Labour-3a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Head Man
0.002
no.
800.00
1.60
Labour, Unskill/ Ordinary
0.388
no.
550.00
213.40
Misc. Sundry-Lab Unskill/
0.004
no.
550.00
2.20
Sub-Total(83)
217.20
217.20
Total(1)
217.20
Add over head on Total(1)
3.5 %
7.60
Add Profit on Total(1)
10.0 %
21.72
Total(2)
246.52
Add VAT on Unit Price
7.5 %
19.99
Unit Price
266.51
Say
266.84
per cum