BREAKDOWN OF UNIT PRICE |
Item:1632570. Clay cover 0-5m height 90% Compac |
Basis:1cum | |
22.Misc-2 |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Diesel/ Fuel | 0.286 | ltr |
109.00 | |
|
|
Sub-Total(22) |
31.17
|
31.17
|
23.Misc-3 |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Lubricant (Mobil Oil) | 0.014 | ltr |
500.00 | |
|
|
Sub-Total(23) |
7.00
|
7.00
|
70.Equipment-0 |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
B.dozer/Roller/Comp:150HP | 0.002 | no. |
6900.00 | |
|
|
Sub-Total(70) |
13.80
|
13.80
|
83.Labour-3a |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Head Man | 0.002 | no. |
800.00 | |
|
Labour, Unskill/ Ordinary | 0.415 | no. |
550.00 | |
|
Misc. Sundry-Lab Unskill/ | 0.004 | no. |
550.00 | |
|
|
Sub-Total(83) |
232.05
|
232.05
|
84.Labour-4 |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Operator, Dozer/Roler/Com | 0.002 | no. |
950.00 | |
|
|
Sub-Total(84) |
1.90
|
1.90
|
|
|
|
Total(1) |
|
285.92 |
|
Add over head on Total(1)
|
3.5 % |
10.01 |
|
Add Profit on Total(1) |
10.0 % |
28.59
|
|
|
|
Total(2) |
|
324.52 |
|
Add VAT on Unit Price |
7.5 % |
26.31 |
|
|
|
Unit Price |
|
350.84
|
|
|
|
Say |
351.22 |
per cum |