BREAKDOWN OF UNIT PRICE
Item:1632570. Clay cover 0-5m height 90% Compac
Basis:1cum
22.Misc-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Diesel/ Fuel
0.286
ltr
109.00
31.17
Sub-Total(22)
31.17
31.17
23.Misc-3
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Lubricant (Mobil Oil)
0.014
ltr
500.00
7.00
Sub-Total(23)
7.00
7.00
70.Equipment-0
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
B.dozer/Roller/Comp:150HP
0.002
no.
6900.00
13.80
Sub-Total(70)
13.80
13.80
83.Labour-3a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Head Man
0.002
no.
800.00
1.60
Labour, Unskill/ Ordinary
0.415
no.
550.00
228.25
Misc. Sundry-Lab Unskill/
0.004
no.
550.00
2.20
Sub-Total(83)
232.05
232.05
84.Labour-4
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Operator, Dozer/Roler/Com
0.002
no.
950.00
1.90
Sub-Total(84)
1.90
1.90
Total(1)
285.92
Add over head on Total(1)
3.5 %
10.01
Add Profit on Total(1)
10.0 %
28.59
Total(2)
324.52
Add VAT on Unit Price
7.5 %
26.31
Unit Price
350.84
Say
351.22
per cum