Return Main Menu

RHD RATE SCHEDULE-2022 Updating..
Click on Code to see the analysis or Go Home Profit=10%, Overhead=3.5%, VAT=5.5%
04 Preliminary and Misc. Work
Code Item Unit Cost(Tk.) Unit Rate(Tk.)
0418000 Prepartion Site, remove soil-15cm Sqm
36.00
44.52
0420000 Supply, fix Bamboo Gauge-6-9cm D m
102.00
124.89
0421010 Supply, fix Wood Gauge 150x25mm m
627.00
769.47
0421020 Supply, fix Wood Gauge 100x25mm m
466.00
571.98
0423000 Supply,fix Triang Wood Gauge 15cm m
1265.00
1552.79
0424000 Wood Gauge Post 2.8m 15-20cm, 1.8 each
1237.00
1517.62
0426000 Fix Water Level Gauge to Balli Po each
249.00
305.66
0428010 Concrett Gauge, Painting 150x25mm m
89.00
108.98
0428020 Concrete Gauge, Painting 100x25mm m
61.00
74.28
0429000 Repair Cement Concrete Gauge m
57.00
70.30
0431000 Bamboo Sounding Rod 7.5cm D, 450m each
359.00
440.13
0432000 Supp Bamboo Peg 6cm D, 0.45-0.75m each
33.00
41.03
0433000 Fix Bamboo Peg 0.45-0.75 m Long each
4.00
4.59
0440010 Water Hyacinth Remove-Scattered sqm
4.00
4.59
0440020 Water Hyacinth Remove-Packed sqm
8.00
10.19
0441010 Cut Tree, Uproot 30cm-1m Girth each
278.00
340.81
0441020 Cut Tree, Uproot 1.0 -1.5 m Girth each
371.00
454.66
0441030 Cut Tree, Uproot above 1.5m Girth each
963.00
1182.16
0444010 Cut,Clear Uprooting Tree-Ordinary sqm
3.00
3.44
0444020 Cut,Clear Uprooting Tree-Thick sqm
4.00
4.59
0445000 Cut, Uproot, Remov Bamboo Cluster sqm
33.00
40.90
0446000 Cut, Uproot, Remove Cane Jungle sqm
17.00
20.45
0447010 Supply Nylon Rope Cross sec 6mm D m
167.00
205.07
0447020 Supply Nylon Rope Cros sec 12mm D m
18.00
21.72
0460010 Provide Cork sheet Expan Jnt-25mm sqm
148.00
181.94
0460020 Provide Cork sheet Expan Jnt-20mm sqm
131.00
161.08
0462010 Fill Expn Jnt sand,bitu-40mm-25mm m
95.00
116.51
0462020 Fill Expn Jnt sand,bitu-40mm-20mm m
76.00
93.25
0472040 Hiring of Speed Boat hr
488.00
598.18
0472050 Hiring of Engine Boat hr
308.00
377.31
0475010 Cost of Fuel for Speed Boat hr
3250.00
3987.84
0475020 Cost of Fuel for Engine Boat hr
365.00
447.25
0480000 75mm Brick work (1:3), 1st Class sqm
715.00
876.96
0480500 125mm Jally Brick work (1:4) sqm
716.00
878.21
0481010 Treatd Wood Flap Gate 0.75-1.2mD each
6903.00
8469.75
0481020 Treatd Wood Flap Gate above 1.2mD each
11673.00
14323.56
0481500 Supply Woodn Fall Board/ Stop Log cum
83171.00
102053.43